Parking lot project day 25, Friday, Aug. 14: DONE! The striping company came out this morning and painted the lines on t...
08/16/2026

Parking lot project day 25, Friday, Aug. 14: DONE! The striping company came out this morning and painted the lines on the lot. I noticed that, just like painting a room, the prep time takes way longer than the actual painting. They were done about 11:00 and said the paint would dry quickly since it was a warm, sunny day. I checked at 12:30 and it was completely dry, so I took in all the cones and admired our lovely new parking lot. We'll all get to enjoy it this Sunday - and every day going forward!

Parking lot project day 21 & 22: Second and final layer of pavement was laid on Monday, and Food Pantry was held on Tues...
08/12/2026

Parking lot project day 21 & 22: Second and final layer of pavement was laid on Monday, and Food Pantry was held on Tuesday. The first photo is actually the last one for Monday, but I liked it so much, I put it first. The rest are in the order they were taken.

First, American Asphalt sprayed on a tack coat, then they took time to mark the parking lot with white paint. All the long straight lines were done the old fashioned way, a long piece of string held straight between two people, while a third marked it with paint.

Then the paving, which had a lot of men very busy, both driving and working on equipment, and also working with hand tools, like shovels and specialized rakes.

They started at 10 in the morning, and finished just after 5. We now have beautiful pavement! But it isn't cured, so it is susceptible to damage. It's really important that we make sure our cars are moving before turning the wheels for the next few weeks.

Despite our food pantry volunteers telling people that, there was still some damage to the lot today. The last two pictures show a couple of the damaged spots. Because of this, we have decided to keep the lot closed one more day to give it a little more time to cure. We'll take up the cones Thursday morning, and we can park on the lot then.

Later, it will be closed a day for striping (possibly Friday or one day next week), then the parking lot resurfacing project will be done!

Parking lot project days 18 - 20: The pavement has been curing, in preparation for the second and final layer of asphalt...
08/07/2026

Parking lot project days 18 - 20: The pavement has been curing, in preparation for the second and final layer of asphalt. We're hoping to see that next week, on any day but Tuesday, which is food pantry day (2nd and 4th Tuesdays).

After the final layer of asphalt, the lot will cure for a few days more, then the striping crew will do their thing, then we're done! But for now, we're happy with our beautiful first layer of pavement, and we can use the lot as needed.

UPDATE: American Asphalt will be out Monday afternoon to lay the final layer of asphalt. We'll put out traffic cones to block the parking lot entrances Sunday afternoon. If you need access to the church (like food pantry deliveries) on Sunday afternoon or Monday morning, just move the cones while you drive in or out, but be sure to put them back right away.

Parking lot project day 17: Good morning! We left yesterday just after 4 pm, guys were still working in the parking lot,...
08/04/2026

Parking lot project day 17: Good morning! We left yesterday just after 4 pm, guys were still working in the parking lot, but it wasn't even half done. We had been told that they would finish this morning.

So I mindlessly parked across the street this morning, gathered my stuff, stood up and faced the church... And saw solid blacktop across the whole parking lot! And no construction equipment either, it was quiet.

It was also starting to spit rain, so I promptly got back in my car and moved closer to the church door. We can drive and park on this, so food pantry people, you're good for deliveries.

Second round of pavement should be later this week.

Parking lot project day 16: Pavement! Last week, the weather forecast predicted rain for today, so American Asphalt said...
08/04/2026

Parking lot project day 16: Pavement! Last week, the weather forecast predicted rain for today, so American Asphalt said they would probably start Tuesday. As we all know, today was a beautiful sunny day (weather forecasts!).

A few guys from American Asphalt showed up in the morning with a big heavy purple truck to check the lot. The truck drove slowly around the lot (forward, then back...) and the asphalt guys walked beside it, watching for any soft spots.

The lot passed muster, so they asked if we minded them starting this afternoon. No problem! And I was given permission to take as many photos as I wanted, so I did. And it was fascinating to see.

The big paving machine has controls on both sides, and the man driving it moves from the left seat to the right seat as needed so he can see to lay the pavement right up to the curb. Two guys ride the back apron (or whatever it's called) doing their jobs, and two or three more guys stay busy with rakes and whatever other tools behind and beside the machine. These guys stay busy. I doubt they need a gym for fitness!

They expect to be back tomorrow morning to finish this layer, or "lift". Then a few days later, the second lift. Then a few days after that, striping, and we'll be done!

Parking lot project day 15: The shaping crew from American Asphalt were hard at work when I arrived at 7:30 this morning...
07/31/2026

Parking lot project day 15: The shaping crew from American Asphalt were hard at work when I arrived at 7:30 this morning. I took the first photo just after getting out of my car, you can see 3 guys working with shovels and scrapers while another one is busy with heavy equipment. The crew was done and gone by 10:30 this morning, leaving a surface ready for asphalt.

We *can* use the parking lot on Sunday. This should be the last Sunday when we'll be dealing with a dirt and gravel surface.

Parking lot project day 14: The shaping crew and their equipment arrived around noon, and they were still working when I...
07/31/2026

Parking lot project day 14: The shaping crew and their equipment arrived around noon, and they were still working when I left at 5:00. It was a busy day in the office so I got only a few pics - I did not get one of the guy surveying the lot at the start, nor did I get one of the guy with the shovel, who stayed busy along the edge of the lot the entire time.

Parking lot project day 13: "Wait for the Lord; be strong and take heart and wait..." Ps 27:14Today was another quiet da...
07/30/2026

Parking lot project day 13: "Wait for the Lord; be strong and take heart and wait..." Ps 27:14

Today was another quiet day of waiting, but that should change tomorrow. The asphalt company hopes to get their "shaping crew" on site tomorrow to do the final grading, which they think will take most of the day. Then Friday should be another quiet day, then they plan to look at laying the first layer of blacktop on Monday.

Parking lot project day 12: Food pantry! Construction pause continued so we could take time to feed our neighbors in nee...
07/29/2026

Parking lot project day 12: Food pantry! Construction pause continued so we could take time to feed our neighbors in need, with the help of church and community volunteers and donations.

The gravel/dirt surface didn't bother the cars, but it was a hard slog for the carts - which didn't stop our volunteers, they just worked harder to take food to people's cars. Hopefully the parking lot will be done before the next food pantry, which will be on August 11 (the 2nd Tuesday of the month) at 1:00 pm.

Parking lot project day 11: "To everything there is a season and a time for every purpose under heaven." Ecc 3:1Today th...
07/27/2026

Parking lot project day 11: "To everything there is a season and a time for every purpose under heaven." Ecc 3:1

Today there was no construction work, but there was preparation for tomorrow's food pantry. Held twice a month, First Presbyterian Church and community volunteers provide food for around 200 of our Wausau area neighbors in need, on every 2nd and 4th Tuesday. Our parking lot will be busy tomorrow, but not with construction.

The photo below shows bags of food lined up in our basement, ready to be distributed tomorrow. If you would like to contribute to this ongoing effort, you can use the link below for a donation, or talk to Chuck (or call the church office) about helping.

https://onrealm.org/firstpreswausau/-/form/give/pantry

Address

406 Grant Street
Wausau, WI
54403

Opening Hours

Monday 9am - 3pm
Tuesday 9am - 3pm
Wednesday 9am - 3pm
Thursday 9am - 3pm
Sunday 8:30am - 12pm