09/08/2026
TEMPLE TUESDAY | September 8, 2026
The Vancouver Washington Temple is nearly fully dried in after crews installed the exterior doors, windows and most of the waterproofing this past week, just ahead of the storms. The waterproofing worked as intended through the rain.
Inside, the third floor is now sheetrocked and painted as crews begin installing HVAC equipment. Framing for one of the temple’s barrel ceilings is complete, and work is beginning on another in the sealing room.
Two additional containers of exterior stone arrived this week, while stone installation continues around the southeast corner of the temple.
https://myoc.io/