09/08/2026

TEMPLE TUESDAY | September 8, 2026

The Vancouver Washington Temple is nearly fully dried in after crews installed the exterior doors, windows and most of the waterproofing this past week, just ahead of the storms. The waterproofing worked as intended through the rain.

Inside, the third floor is now sheetrocked and painted as crews begin installing HVAC equipment. Framing for one of the temple’s barrel ceilings is complete, and work is beginning on another in the sealing room.

Two additional containers of exterior stone arrived this week, while stone installation continues around the southeast corner of the temple.
https://myoc.io/

Sister Alex Walsh from the Meadows ward headed out this morning to the great land of Layton Utah to serve the Lord for 1...
09/02/2026

Sister Alex Walsh from the Meadows ward headed out this morning to the great land of Layton Utah to serve the Lord for 18 months! You will be great Alex!🩷

09/01/2026

TEMPLE TUESDAY | September 1, 2026

The exterior stone mock-up on the northwest corner of the Vancouver Washington Temple is nearing completion as crews finish grouting the stone before it is reviewed by the architect. Crews are also installing stone on the southwest corner, where it is visible from SE 20th Street.

All of the windows are now installed, including the large celestial and sealing room windows, as well as the steeple windows. The windows on the north and south ends are scheduled for water testing this week.

Inside, work on the interior walls continues on the third floor, while the north end of the first floor is almost ready for sheetrock. In the baptistry, watertightness testing of the font is complete and the water has been drained. Ceiling framing is now in progress.
https://myoc.io/

TEMPLE TUESDAY | August 25, 2026On the south side of the Vancouver Washington Temple, the final piece of glass in the la...
08/25/2026

TEMPLE TUESDAY | August 25, 2026

On the south side of the Vancouver Washington Temple, the final piece of glass in the large sealing room window is now set in place. Exterior cladding now surrounds the window, while crews are grouting the stone on the west side of the temple.

Inside, sheetrocking continues on the third floor. New construction lighting was installed in the sealing and celestial rooms to provide additional light as interior work continues.

At the maintenance building, insulation is finished and sheetrock work is underway. Crews are also connecting controls and other components to the chiller, part of the temple’s cooling system.

(Photos courtesy of Scott Ririe, Ridgefield Washington Stake)
https://myoc.io/

08/18/2026

TEMPLE TUESDAY | August 18, 2026

The heavy steel framing for the portico at the main entrance of the Vancouver Washington Temple is now complete. Steel erectors spent the past week constructing the framework for the temple’s future main entrance.

On the south side of the temple, glass installation is nearing completion in the sealing room window, with the rectangular sections in place. Inside, sheetrock installation is progressing on the third floor. At the maintenance building, sheetrock work is also underway, along with installation of the chiller, part of the temple’s cooling system.

(Video courtesy of Scott Ririe, Ridgefield Washington Stake)
https://myoc.io/

Kevin Bennion has returned home from his mission in Adelaide Australia! Welcome home!!🦘🇦🇺
08/16/2026

Kevin Bennion has returned home from his mission in Adelaide Australia! Welcome home!!🦘🇦🇺

The Family Search booth is the best booth at the Clark County Fair! Have you checked it out yet?🎢🍦🌭
08/12/2026

The Family Search booth is the best booth at the Clark County Fair! Have you checked it out yet?🎢🍦🌭

TEMPLE TUESDAY | August 11, 2026This week, steel erectors are back on site as structural framing begins for the portico ...
08/11/2026

TEMPLE TUESDAY | August 11, 2026

This week, steel erectors are back on site as structural framing begins for the portico on the south end of the Vancouver Washington Temple. A portico is a covered structure at a building's entrance, and this one will form the temple's future main entrance.

Inside, windows are being installed in the sealing room on the south end of the temple. Sheetrock work is also beginning in the maintenance building, while additional steel framing, scaffolding and stonework continue throughout the site.

(Photos courtesy of Scott Ririe, Ridgefield Washington Stake)
https://myoc.io/

Don’t forget to check out the Family History booth at the Clark County fair!🎡☀️
08/07/2026

Don’t forget to check out the Family History booth at the Clark County fair!🎡☀️

08/04/2026

TEMPLE TUESDAY | August 4, 2026

This week, crews are completing trim work around the recently installed windows beneath the spire on the north side of the Vancouver Washington Temple. Inside, the baptismal font remains filled with water during a watertightness test while construction progresses on internal building systems.