11/07/2026
"The trestle bents are entirely of steel and will remain in the concrete," Engineering News-Record wrote of the work at Grand Coulee Dam, Washington, in January 1936.
The bents were the steel frames that formed the legs of two railroad trestles. They stood on the bedrock of the Columbia River canyon, where the Bureau of Reclamation's dam was beginning to rise, and the concrete was already being poured around them.
The reason was reach. The dam's base would run 3,000 feet across the canyon, and every bucket of concrete had to be set down in its place along it. So the trestles were built inside the dam's own outline, one high near its upstream face and one low near its downstream toe. Each was about 30 feet wide, with three standard-gauge tracks and, outside them, rails for a gantry crane, a crane that straddled the tracks so the trains could run beneath it. Standing on bedrock, a 1941 account said, they let those cranes "cover a 500-ft. strip across the canyon."
Concrete left the mixing plant in steel buckets of four cubic yards, riding on flatcars behind 10-ton diesel locomotives. Cranes on the trestles lifted the buckets off the cars, swung them out over the rising blocks and lowered them into the forms. "A great big crane would pick 'em up and put 'em down in the proper place," Rod Hartman remembered.
But the dam grew in lifts of five feet, block beside block, and each lift closed higher around the steel legs. The Bureau said it plainly in its own booklet about the dam: the steel trestles "are buried, and forever lost."
Only the decks, the girders that carried the tracks, were ever taken back out.
Therefore the builders faced a new problem. The base was finished with the old legs inside it, yet the dam still had to climb far above the old tracks. Concrete for the high dam would come from a single new trestle, its deck at elevation 1180, more than 150 feet above the old high one.
In 1938 the contractor for the high dam, Consolidated Builders, Inc., took down what remained of the old trestle. Its deck went to the fabricating plant at Electric City, four miles away, where Bethlehem Steel reframed it. Between June 13 and September 12, Bethlehem's crew of seventy-five steel workers put up the new trestle, about 3,600 feet long. Of its 8,900 tons of steel, 3,200 tons came from the deck of the old one, and some of the old silicon steel beams went into its 60-foot spans. On the site everything was bolted, not riveted, "since the structure was not to be permanent." Contractors and Engineers Monthly wrote that "this trestle job stands out among the record-making performances."
That new trestle is the long line across the face of the dam in this photograph, taken from an Army plane on July 24, 1941. At its left end, the track curves off the dam on steel legs to the concrete mixing plant.
From October 1941, that trestle was taken down from the face of the dam.
The builders never took out the legs of the first two. They stayed where the concrete closed over them, in the base of Grand Coulee Dam.