TEMPLE TUESDAY | September 1, 2026
The exterior stone mock-up on the northwest corner of the Vancouver Washington Temple is nearing completion as crews finish grouting the stone before it is reviewed by the architect. Crews are also installing stone on the southwest corner, where it is visible from SE 20th Street.
All of the windows are now installed, including the large celestial and sealing room windows, as well as the steeple windows. The windows on the north and south ends are scheduled for water testing this week.
Inside, work on the interior walls continues on the third floor, while the north end of the first floor is almost ready for sheetrock. In the baptistry, watertightness testing of the font is complete and the water has been drained. Ceiling framing is now in progress.