01/17/2024
We submitted Solar Panel project plans to the city of Laguna Woods, the Fire authority, and SCE. We got an approval with the fire department. We expect the SCE application to take another two to three months to get approved. The city approved everything but the ballast racks, this is usually the toughest part to get approved with the cities because the racking has no penetrations. They are asking for some more detail and more specifications on the blocks. We are adding more detail and further explanation to the plans and resubmitting them next week. This project was made possible in part by the Adamah Climate Action Fund. Here is link to: adamah.org/coalition.