Day 4‘s progress!
I’m sorry we didn’t post yesterday but here is what happened!!!
Posts are set to put up our new sign. I’m so excited to see it mounted!
The outdoor crew went around trimming low/dead limbs and hauling them off. They also finished filling potholes on the Levering St side. The pothole in the picture is ove 8ft long, over 2ft wide, and about 4 or more inches deep!
A closet was built around the furnace, hiding it and providing some storage space. the entrance to the bathrooms was finished off and doors hung. And new sills under the windows in the lighthouse room were installed.
Not pictured were the dozens of old florescent fixtures and other scrap metal that was hauled to the recycling, and the 4 old air units that were taken apart in order to be recycled.
Once again a ton of work done in one day. The team is spending the weekend doing fun activities and resting. They will hit things again Monday!