Ariya Vihara Building Project

Ariya Vihara Building Project Progress Update of Ariya Vihara Building Project
https://ariyavihara.org/ariya-vihara-building-project/

Dhammapada verse 122

One should not think lightly of doing good, imagining 'A little will not affect me'; just as a water-jar is filled up by falling drops of rain, so also, the wise one is filled up with merit, by accumulating it little by little.
莫輕視善行,以為「小善不會為我帶來果報」;如同滴水能注滿水瓶,智者累積小善至福德滿盈。
法句經 偈頌次 122

Casting of the Sīmā Hall columns is in progress.
28/04/2026

Casting of the Sīmā Hall columns is in progress.

Slab casting of the lower ground floor is completed.
28/04/2026

Slab casting of the lower ground floor is completed.

16/04/2026

The video shows the progress of the Ariya Vihara Building Project up to April 2026. Video by Sis. Wendy Khaw and Zense

Rebar works installation, backfilling and compaction of earth at lower ground slab are in progress.
08/04/2026

Rebar works installation, backfilling and compaction of earth at lower ground slab are in progress.

Formworks, rebar modifications and lean concreting are in progress.
31/03/2026

Formworks, rebar modifications and lean concreting are in progress.

Formwork and installation of PC Strand are in progress at lower ground
05/03/2026

Formwork and installation of PC Strand are in progress at lower ground

03/02/2026
Lower ground beam formwork works are in progress.
16/01/2026

Lower ground beam formwork works are in progress.

Sīmā Hall pilecaps' concreting has been completed. Concreting of other pilecaps are in progress.
08/01/2026

Sīmā Hall pilecaps' concreting has been completed. Concreting of other pilecaps are in progress.

We are happy to share that the foundation piling and sheet pile retaining wall works have been successfully completed. E...
02/01/2026

We are happy to share that the foundation piling and sheet pile retaining wall works have been successfully completed. Excavation for the pile caps is currently underway, along with the installation of pile cap formwork and rebar.

As we begin the New Year 2026, we wish everyone a year filled with good health, harmony, growth in the Dhamma and smooth progress in all endeavors.

The RIBI road premix is completed and under inspection.
23/10/2025

The RIBI road premix is completed and under inspection.

Address

No. 37-1 & 37-2, Jalan Nautika B U20/B, Seksyen U20, Pusat Komersil TSB, Sg Buloh
Shah Alam
40160

Alerts

Be the first to know and let us send you an email when Ariya Vihara Building Project posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Place Of Worship

Send a message to Ariya Vihara Building Project:

Share