Backfilling of earth is in progress at Sima Hall area.
09/07/2026

Backfilling of earth is in progress at Sima Hall area.

Formworks and rebar works are in progress at the first floor's slab and beams.
08/07/2026

Formworks and rebar works are in progress at the first floor's slab and beams.

30/06/2026

Announcement | 𝐓𝐚𝐱-𝐄𝐱𝐞𝐦𝐩𝐭 𝐒𝐭𝐚𝐭𝐮𝐬 𝐟𝐨𝐫 𝐁𝐮𝐢𝐥𝐝𝐢𝐧𝐠 𝐏𝐫𝐨𝐣𝐞𝐜𝐭

We are pleased to announce that we have obtained a tax-exempt status under Subsection 44(6) of the Income Tax Act 1967 for our Building Project - Tabung Pembinaan Rumah Ibadat Ariya Vihara (TPRI), with effect from 1st June 2026.

We would like to express our sincere thanks and gratitude to the Inland Revenue of Malaysia (LHDN) and the relevant authorities for their approval and support. Donations made towards the TPRI are eligible for tax-exempt receipts, subject to the terms and conditions stipulated by LHDN.

We sincerely thank all devotees, members, donors and kind supporters for your continued generosity and support given to Ariya Vihara.

To ensure your contribution qualifies for a tax-exempt receipt, please make your donations to:
Persatuan Penganut Buddha Ariya Vihara Kuala Lumpur Dan Selangor
Bank: United Overseas Bank (UOB)
Account No: 240-308-872-4

Kindly complete the online form at https://bit.ly/AriyaTPRI and whatsapp your bank slip to the contact numbers stated in the online form to receive your official receipt.

Sādhu, Sādhu, Sādhu! 🙏🙏🙏

16/06/2026
Post tension beams are up, and work continues on at ground floor slab (main building) and Sima Hall.
18/05/2026

Post tension beams are up, and work continues on at ground floor slab (main building) and Sima Hall.

Casting of the Sīmā Hall columns is in progress.
28/04/2026

Casting of the Sīmā Hall columns is in progress.

Slab casting of the lower ground floor is completed.
28/04/2026

Slab casting of the lower ground floor is completed.

16/04/2026

The video shows the progress of the Ariya Vihara Building Project up to April 2026. Video by Sis. Wendy Khaw and Zense

Rebar works installation, backfilling and compaction of earth at lower ground slab are in progress.
08/04/2026

Rebar works installation, backfilling and compaction of earth at lower ground slab are in progress.

Address

No. 37-1 & 37-2, Jalan Nautika B U20/B, Seksyen U20, Pusat Komersil TSB, Sg Buloh
Shah Alam
40160

Alerts

Be the first to know and let us send you an email when Ariya Vihara Building Project posts news and promotions. Your email address will not be used for any other purpose, and you can unsubscribe at any time.

Contact The Place Of Worship

Send a message to Ariya Vihara Building Project:

Shortcuts

Share