05/19/2026
The Fire: On August 27, 2023, The Mission’s 36,000-square-foot main building was lost in a devastating fire. The building housed our junior high, high school, School of Missions, corporate offices, coffee shop, place of worship, and church.
The Cleanup: On August 28, 2023, the city of Tijuana generously provided a dedicated cleanup crew, leading to incredible progress at the fire site.
The Tent: On November 8, 2023, we set up the tent that now hosts our church services and daily devotions.
Breaking Ground: On September 28, 2025, we officially began Phase 2 by breaking ground for our new building. We came together as a church and community to pray over the foundation and make declarations.
Exterior Structure: On April 19, 2026, our local construction team began building the exterior structure of the new building, bringing us almost halfway through Phase 3!
Thank you to everyone who has been rebuilding with us and helping make this possible ❤️